Quarterly Activities/Appendix 5B Cash Flow Report
Released
Released
Announcement PDF
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
ASX:NFL 31st
October 2025
QUARTERLY ACTIVITIES REPORT
FOR THE PERIOD ENDED 30 SEPTEMBER 2025
Norfolk Metals Limited (ASX:NFL) (Norfolk or the Company) is pleased to report on its activities during
the 3-month period ended 30 September 2025.
Highlights of Quarter Ending 30 September 2025
- Maiden Drill Campaign commenced at the Carmen Copper Project (See announcement 13th
August 2025)
- A$3.5m capital raising completed including commitments from Project Operators and Norfolk Board (See
announcement 28th
July 2025)
- Strong capital position at September 30th
2025 with A$3.92m in cash
Highlights post Quarter Ending 30 September 2025
- David Fowler of Transcendence Mining appointed to the board of Norfolk Metals (See announcement 3rd
October 2025)
- RC phase of drilling close to completion with DDH collars pulled forward into the RC phase and new
targets identified (See announcement 30th
October 2025)
Norfolk commences drilling at the Carmen Copper Project
Following grant of drilling permit, on the 13th
August 2025 Norfolk Metals Ltd (Norfolk or the Company)
announced the commencement of the Maiden Drill Campaign at the Carmen Copper Project in Chile.
Up to 5,100m of Diamond Drill Hole (DDH) and Reverse Circulation (RC) drilling to be conducted in two
consecutive programs. The DDH is expected to commence after the completion of the RC drilling.
The RC drilling phase began at the Carmen Main target area, which hosts a historical copper oxide
mineral resource estimate of 5.6Mt at 0.6% Cu reported in accordance with Canadian National
Instrument 43-101 (Carmen NI 43-101 MRE)1,2
(See Annexure A and 31st
March 2025 ASX release). The
RC Phase of drilling will concentrate on targets along strike of the Carmen-Tabaco Thrust Fault system
and confirmation of known mineralisation within the historical resource area, with some twinning of
important historical drill holes.
Norfolk has engaged ALS Laboratories in Chile for analytical work. Samples from the Maiden Drilling
campaign will be sent to Copiapo to be prepared, and subsequent analysis will be completed in
Santiago.
1
Independent Technical Report prepared by SRK Consulting Chile S.A. (SRK) for International PBX Ventures Ltd. (IPBX) published 25 January
2027 (Carmen NI 43-101 MRE).
2
The Carmen NI 43-101 MRE is a historical foreign estimate (within the meaning of the ASX Listing Rules) and is not reported in accordance
with the JORC Code and a Competent Person (within the meaning of the JORC Code) has not done sufficient work to classify the foreign
estimates as Mineral Resources in accordance with the provisions of the JORC Code. It is uncertain that following evaluation and further
exploration work that the foreign estimates will be able to be reported as Mineral Resources in accordance with the provisions of the JORC
Code.
2
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
$3.5m Capital Raise Completed
28th
July 2025 saw the Company announce it had received firm commitments to raise $3.5 million
(before costs) towards funding the Transaction and the continually expanding exploration plans of the
Project (Placement). Norfolk board, Transcendence Mining directors and existing shareholders all
participated in the Placement. The 29th
September 2025 saw the successful completion of the
placement post theEGMheld on the 25th
September 2025 (see ASX news releases fromtheserespective
dates.
The Placement comprised the issue of 28,000,000 new shares in the Company (Shares) using the
Company’s existing placement capacity pursuant to ASX Listing Rules 7.1 (7,806,140 Shares) and 7.1A
(5,204,093 Shares), totalling 13,010,233 via Tranche 1 and 14,989,767 via Tranche 2. Refer to the
Company’s Appendix 3B lodged 28 July 2025, for further details.
The Placement issue price of $0.125 represented a 14.3% discount to the 15-day volume weighted
average price (VWAP) of $0.14.
JP Equity Partners acted as Lead Manager to the Placement.
David Fowler appointed to Norfolk Board
On the 2nd
October 2025, Mr. David Fowler was appointed to the Norfolk board of directors as a Non-
Executive Director. Mr Fowler is a director of Transcendence Mining Pty Ltd (“Transcendence”), the
option vendors and project operators of the Carmen Copper Project (“Carmen”), in Chile. Mr Fowler
brings 35 years of financial & mining industry experience with a decade of operational experience in
Chile; also speaking fluent Spanish.
As theCFOat MerdekaCopper Gold,Mr Fowler hasbeen instrumental in funding thegrowth of thegroup
from a single asset gold project into a multi-commodity business with an enterprise value of US$9
Billion in 2024. He has led debt & equity funding processes to raise more than US$400m in equity and
US$4B in debt funding during this time. Mr Fowler has worked in numerous other executive roles
including CEO of Orosur Mining, a South American focused gold company producing 100,000 ounces
of gold per annum and Finders Resources Limited that operated the 20,000-tonne per annum Wetar
copper heap leach project.
Overview – Carmen Copper Project
The Carmen Copper Project is in the Huasco Province, Atacama Region in Chile (Figure 1). The Project
encompasses twenty-two contiguous exploration and exploitation licenses totalling 46.6km2
.
The Project hosts multiple mineralised targets over an extensive 15km plus strike length (over two
regional belts) with intensive copper mineralisation from surface.
Only 16km to the northeast of the CCP is the Nueva Unión joint venture between Teck and Newmont.
Nueva Unión is currently developing the multi-billion-dollar Relincho and Fortuna (previously called El
Morro) porphyry deposits (Figure 1).
The Carmen Copper Project contains 149 historical holes of reverse circulation (RC) and diamond
drilling (DD) totalling 10,513.35 meters. From the late 1800’s to 1960’s there was small scale high-grade
3
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
artisanal copper mining in the area. Between 1962 and 1964, Minera Metalmine Ltda. (MML) drilled 56
shallow percussion holes for 1,680 meters to evaluate leachable copper resources for open pit mining.
In 2002, Minera IPBX Chile Limitada (MIPBX) of International PBX Ventures Limited (IPBX) explored the
Project. Work by IPBX initially included 29 km of ground magnetics and 30 km of induced polarization
(IP), defining a NE striking, elongated chargeability anomaly 100 - 300 meters wide and 2,400 meters
long in the area drilled by MML. In mid-2003, IPBX drilled 25 RC and DD holes, to investigate the IP
chargeability anomaly over Carmen, with two holes also into Tabaco for 3,685.95m. Most Carmen holes
intersected some copper bearing sulphides, and several returned promising Cu grades in oxides.
Figure 1: Carmen Cu Project Location
In early 2004, mapping and additional soil sampling by IPBX confirmed the extent of the copper oxide
zone over the chargeability anomaly and delineated further Cu + Au anomalies to the west and
stratigraphically up section.
In 2006, IPBX completed 67 DD holes for 4,650.2 meters, and infilled ~600 meters of strike at Carmen
at ~ 50m spacing, with step out holes over a further 400 meters of strike, plus a few scout holes on the
northern hanging wall of the Carmen-Tabaco thrust fault and at the Tabaco project area. At Carmen,
thick sulphide zones were confirmed in several holes, but not all holes testing areas of known oxide
confirmed the historic work that had returned results previously.
In January 2007, SRK delivered the Carmen NI 43-101 MRE (See announcement 31st
March 2025).
4
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
Maiden Drilling Campaign Update
Post the quarter end on the 30th
of October the Company released an update to market including RC
Drilling having been expanded to include confirmatory drilling and additional targets added to the
program (Figure 2). The highlights are as follows:
1. Norfolk continues to advance the Maiden RC and DDH drilling program, currently drilling the 30th of
up to 50 planned holes; the RC program phase is expected to conclude with 34 holes and all remaining
holes will be DDH.
2. The RC drilling is now concentrating on confirming historical holes along the Tabaco Thrust to validate
higher-grade historical intercepts. This work has been brought forward from the confirmatory collars
planned for the DDH component.
3. Higueritas Belt access and reconnaissance mapping has identified areas exhibiting visible copper
oxides outcrops spatially associated with structures and coincident with a strong IP chargeability
anomaly. Surface sampling of the observed oxide mineralisation has been conducted and sent for
analysis along with two RC holes planned for immediate drilling.
4. Several historic 2006 IPBX diamond holes have been selected to be quarter cut for re-assay to confirm
historic intersections for copper & gold
Figure 2: Drill Location Plan showing location of RC drill holes CCRC-25-001 through CCRC-25-029
(All assays and grades displayed from historical drilling)
5
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
Existing project developments in the reporting period
Both the Orroroo Uranium Project and the Roger River Project have progressed with further
consideration given to future exploration and reporting obligations however the focus was limited during
the quarter due to drilling preparation and commencement at the Carmen Copper Project.
Norfolk has previously announced the intention to consider further geophysics for target generation at
the Orroroo Uranium Project (Figure 4). The Company continues to work with Orroroo stakeholders via
the Company local correspondent to build a data base of existing water wells that have the potential to
access with a geophysical probe (gamma) without interrupting or damaging the water infrastructure
services the wells provide. This work is still progressing with finalisation of specific wells located within
areas of interest that can also be accessed when considering all requirements to be met with freehold
landowner engagements and any considerations of water supply while conducting surveys.
The Orroroo Uranium Project comprises three granted exploration licenses, EL6552, EL6814 and
EL6948, which together cover 723km2, located approximately 274km northwest of the capital city of
Adelaide, South Australia within the Walloway Basin, which is an elongate Tertiary Basin approximately
50km long and up to 15km wide. It consists of Tertiary and Quaternary sediments unconformably
underlain by Adelaidian basement.
Figure 4: Orroroo Uranium Project
Revised expenditure commitments were previously established for Tasmanian permits EL20/2020 and
proposals wereprepared for futuredrilling upon receipt of all required approvals. Planning for future drill
testing of priority targets continues; contingent on final approvals and access.
During the quarter, the Company elected to surrender EL17/2021 rather than extend the tenement due
to the increased level of committed expenditure, and the tenement being considered non-core to the
Company with the progression of the Carmen Copper Project.
6
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
The Roger River Project comprises of the granted exploration license EL20/2020, which covers 26km2
,
located 410km northwest of the capital city of Hobart, Tasmania. The Project is prospective for gold and
copper as indicated by the intense silicification, argillisation and diatreme breccias in close proximity
to the Roger River Fault along with carbonate-rich host rocks.
Figure 5: Roger River Project
Financials
The cash flows relating to the September 2025 quarter included a total of $1,087k in exploration and
evaluation spend on the Carmen Copper, Roger River and Orroroo projects and $373k in staff, corporate
and admin costs managing the corporate requirements of the Company. There were no substantive
mining production and development activities during the Quarter.
The Company had a closing cash balance of $3.92 million.
For the purposes of section 6 of the Appendix 5B, all payments made to related parties are for director
and consulting fees.
7
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
Tenement Status
The Company confirms that all of its tenements remain in good standing.
Tenement ID Holder/Applicant Interest at start
of quarter (%)
Interest at end
of quarter (%)
EL20/2020 Roger River Resources Pty Ltd 100% 100%
EL17/2021 Roger River Resources Pty Ltd 100% 0%
EL6552 Black Lake Pty Ltd 100% 100%
EL6814 Black Lake Pty Ltd 100% 100%
EL6948 Black Lake Pty Ltd 100% 100%
END
This announcement has been authorised by the directors of Norfolk Metals Ltd
About Norfolk Metals
The Carmen Copper Project (CCP) is located in the Huasco Province, Atacama Region in Chile. The Project
encompasses twenty-two contiguous exploration and exploitation licenses totalling 46.6km2
. There are multiple
mineralised targets over an extensive strike length with intensive copper mineralisation from surface. Only 16km
to the northeast of the CCP is the Nueva Unión joint venture between Teck and Newmont. Nueva Unión is currently
developing the multi-billion-dollar Relincho and Fortuna (previously called El Morro) deposits. Whilst the CCP
currently presents as a copper oxide project with highly soluble copper oxide mineralisation from surface; it also
hosts significant sulphide potential as demonstrated in historical drill intercepts that warrant further investigation
and follow-up drilling programs. Norfolk is aiming to establish the Carmen Copper Project as a low-cost, high-
margin, value-accretive copper heap leaching operation producing copper cathode at the mine gate.
The Orroroo Uranium Project comprises three granted exploration licenses, EL6552, EL6814 and EL6948, which
together cover 723km2
, located approximately 274km northwest of the capital city of Adelaide, South Australia
within the Walloway Basin, which is an elongate Tertiary Basin approximately 50km long and up to 15km wide. It
consists of Tertiary and Quaternary sediments unconformably underlain by Adelaidean basement.
The Roger River Project is comprised of one granted exploration license EL20/2020 which covers 26km2
, located
410km northwest of the capital city of Hobart, Tasmania. The Project is prospective for gold and copper as
indicated by the intense silicification, argillisation and diatreme breccias in close proximity to the Roger River Fault
along with carbonate-rich host rocks.
For further information please visit www.norfolkmetals.com.au
Forward Looking Statements
This announcement includes “forward looking statements” within the meaning of securities laws of applicable
jurisdictions. Forward looking statements can be identified by the use of forward looking terminology, including,
without limitation, the terms “believes”, “estimates”, “anticipates”, “expects”, “predicts”, “intends”, “plans”,
“goals”,“targets”,“aims”,“outlook”,“guidance”,“forecasts”,“may”,“will”,“would”,“could”or“should”or, in each
case, their negative or other variations or comparable terminology. These forward looking statements include all
matters that are not historical facts. By their nature, forward looking statements involve known and unknown risks,
uncertainties and other factors because they relate to events and depend on circumstances that may or may not
occur in the future and may be beyond the Company’s ability to control or predict which may cause the actual
results or performance of the Company to be materially different from the results or performance expressed or
implied by such forward-looking statements. Forward looking statements are based on assumptions and are not
guarantees or predictions of future performance. No representation is made that any of these statements or
8
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
projections will come to pass or that any forecast result will be achieved, nor as to their accuracy, completeness
or correctness. Similarly, no representation is given that the assumptions upon which forward looking statements
may be based are reasonable. Forward looking statements speak only as at the date of this release and the
Company and its affiliates, related bodies corporate (as that term is defined in the Corporations Act) and its
directors, employees, officers, representatives, agents, partners, consultants and advisers disclaim any
obligations or undertakings to release any update of, or revisions to, any forward-looking statements in this
announcement.
Disclaimers
No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or
correctness of the information, opinions and conclusions contained in this release. To the maximum extent
permitted by law, none of the Company, its related bodies corporate, shareholders or respective directors,
officers, employees, agents or advisors, nor any other person accepts any liability, including, without limitation,
any liability arising out of fault or negligence for any loss arising from the use of information contained in this
release. The Company will not update or keep current the information contained in this release or to correct any
inaccuracy or omission which may become apparent, or to furnish any person with any further information. Any
opinions express in this release are subject to change without further notice.
No representation or warranty, express or implied, is made as to the fairness, accuracy, completeness or
correctness of the information, opinions and conclusions contained in this release. To the maximum extent
permitted by law, none of the Company, its related bodies corporate, shareholders or respective directors,
officers, employees, agents or advisors, nor any other person accepts any liability, including, without limitation,
any liability arising out of fault or negligence for any loss arising from the use of information contained in this
release.
This release does not constitute an invitation, offer or recommendation to apply for or purchase securities and
does not contain any application form for securities. This release does not constitute an advertisement for an
offer or proposed offer of securities. Neither this release nor anything contained in it shall form the basis of any
contract or commitment and it is not intended to induce or solicit any person to engage in, or refrain from engaging
in, any transaction.
Streamline Competent Person’s Statement
This report contains information extracted from previous ASX releases which are referenced in the report. The
Company is not aware of any new information or data that materially affects the information included in the
original market announcements.
The Company confirms that the form and content in which the Competent Person’s findings are presented have
not been materially modified from the original market announcements
Annexure A – NI 43-101 - Mineral Resources and Reserves
Compliance Statements (information required by ASX Listing Rule 5.13)
The Mineral Resource Estimate at the Carmen Copper Project is a foreign estimate prepared in accordance with
Canadian National Instrument 43-101 and is not reported in accordance with the JORC Code 2012. A competent
person has not done sufficient work to classify the foreign estimate as a mineral resource in accordance with the
JORC Code 2012, and it is uncertain whether further evaluation and exploration will result in an estimate
reportable under the JORC Code 2012.
The Company initially announced the foreign estimate for the Carmen Copper Project on 31 March 2025 in
accordance with ASX Listing Rule 5.12. The Company confirms that the supporting information included in the
announcement of 31 March 2025 continues to apply and has not materially changed. The information in this
9
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
section relates solely to the foreign estimate previously disclosed under ASX Listing Rule 5.12 and does not
constitute new exploration results.
Norfolk confirms that it is not in possession of any new information or data relating to the foreign estimate that
materially impacts the reliability of the estimates or Norfolk’s ability to verify the foreign estimates as mineral
estimates in accordance with Appendix 5A (JORC Code).
It is the Company’s intention to validate the results of the foreign estimate through re-logging of historical drill
holes and completion of the proposed maiden drilling program. The results of the maiden drill program (including
twinning of historical holes) will determine the next phase of drilling to facilitate the course towards the Company’s
aim to construct a 2012 JORC Resource estimate. In addition, it is also the intent of the Company to use the rejects
(remaining samples not sent for analysis) from the RC drilling to conduct additional metallurgical studies to
confirm the leaching results of the previous study and possibly determine a more suitable/economic leaching
strategy.
Table: Carmen NI 43-101 MRE
Cautionary Statement - Carmen NI 43-101 MRE
In accordance with ASX Listing Rule 5.12.9, the Company provides the following cautionary statement regarding
the Carmen NI 43-101 MRE shown in the Table:
• The Carmen NI 43-101 MRE is a foreign estimate and is not reported in accordance with the JORC Code;
• A competent person has not done sufficient work to classify the foreign estimate as a mineral resources in
accordance with the JORC Code; and
• It is uncertain that following evaluation and/or further exploration work that the foreign estimate will be able
to be reported as mineral resources in accordance with the JORC Code.
Within the Carmen Tabaco Belt, the Carmen NI 43-101 MRE has been defined over 600m of strike, to a depth of
30m in the Carmen Oxide Zone (COZ). The Carmen NI 43-101 MRE excludes historic higher-grade drilling and
covers no more than 20% of the COZ. The COZ presents as potentially continuous between drill holes and sections
along structural and lithology-controlled zones, which are mainly sub-parallel to the Tabaco Thrust.
Tonnage
(kilotonnes)
Copper
grade (%)
Contained
Metal
Tonnage
(kilotonnes)
Copper grade
(%)
Contained
Metal
Tonnage
(kilotonnes)
Copper grade
(%)
Contained
Metal
Measured - - - - - -
Indicated 1,827.80 0.59 1078.40 1,742.60 0.7 1219.82 3,570.40 0.64 2298.22
Total
Measured and
Indicated
1,827.80 0.59 1078.40 1,742.60 0.7 1219.82 3,570.40 0.64 2,298.22
Inferred 836.1 0.59 493.30 1,191.90 0.49 584.03 2,028.00 0.53 1077.33
Total
Resources
2,663.90 0.59 1,571.70 2,934.50 0.61 1803.85 5,598.40 0.60 3,375.55
Resource
Classification
Note: reported at a cut-off grade of 0.2% Cu, not capped
Oxide Zone Secondary Enrichment Total Resource (Oxide+Secondary)
10
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
Fortuna (NI 43-101)
Category
Gold Copper
Tonnes (Millions)
Gold grade
(g/t)
Contained Metal
(Mozs)
Copper grade
(%)
Contained Metal
(Mlbs)
Proved 321.81 0.56 5.82 0.55 3876.59
Probable 277.24 0.35 3.10 0.43 2626.36
Total Reserves 599.05 0.46 8.92 0.49 6502.95
Measured 19.79 0.53 0.34 0.51 223.33
Indicated 72.56 0.38 0.88 0.39 630.00
Inferred 678.07 0.30 6.45 0.35 5,190.00
Total Resources 770.42 0.31 7.67 0.36 6,043.33
Total Reserves +
Resources
1,369.47 0.38 16.59 0.42 12,546.28
Source: https://www.teck.com/news/news-releases/2015/goldcorp-and-teck-combine-el-morro-and-relincho-projects-in-chile
Relincho (NI 43-101)
Category
Copper Molybdenum
Tonnes
(Millions)
Copper
grade (%)
Contained
Metal (Mlbs)
Molybdenum
grade (%)
Contained Metal (Mlbs)
Proved 435.30 0.38 3646.75 0.016 153.55
Probable 803.80 0.37 6556.70 0.018 318.97
Total Reserves 1,239.10 0.37 10,106.65 0.017 464.36
Measured 79.90 0.27 475.60 0.009 15.85
Indicated 317.10 0.34 2376.89 0.012 83.89
Inferred 610.80 0.38 5117.02 0.013 175.06
Total
Resources
1,007.80 0.36 7,969.51 0.012 274.80
Total Reserves
+ Resources
2,246.90 0.37 18,076.16 0.015 739.16
Source: https://www.teck.com/news/news-releases/2015/goldcorp-and-teck-combine-el-morro-and-relincho-projects-in-chile
11
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
Candelaria (NI 43-101)
Source: https://lundinmining.com/news/lundin-mining-announces-2024-mineral-resource-and-123185/
Mantos Blancos (NI 43-101)
Category
Copper Silver
Tonnes
(Millions)
Copper grade
(%)
Contained
Metal (kt)
Silver grade (g/t)
Contained Metal
(kozs)
Proved 72.60 0.78 567 6.41 14968
Probable 50.00 0.57 288 4.57 7339
Total Reserves Sulphides 122.60 0.69 854 5.66 22,307
Proved 2.8 0.36 10
Probable 1.8 0.28 5
Total Reserves Oxide 4.6 0.33 15
Proved
Probable 6.7 0.18 12
Total Reserves Stockpile 6.7 0.18 12
Measured 104.4 0.75 783 6.03 20,234
Indicated 106.5 0.58 618 4.41 15,099
Inferred 20 0.48 96 3.35 2,151
Total Resources Sulphides 230.90 0.65 1,497 5.05 37,484
Measured 22.8 0.34 78
Indicated 28.5 0.26 74
Indicated 6.3 0.18 11
Indicated 3.9 0.19 7
Inferred 8.6 0.25 21
Inferred 2.3 0.19 6
Inferred 3.1 0.19 4
Inferred 4.4 0.17 7
Total Resources Oxides (Dump) 79.90 0.26 208
Total Reserves + Resources 444.70 0.58 2,586.00 5.26 59,791.00
Source: https://capstonecopper.com/wp-content/uploads/2023/01/MB-Technical-Report-Final-Jan-5-2022.pdf
12
ASX ANNOUNCEMENT
Unit 10, 85-87 Forrest Street
Cottesloe WA 6011
ABN: 38 652 438 385
Phone: +61 8 6255 8625
norfolkmetals.com.au
Mantoverde Project (NI 43-101)
Category Copper Gold Cobalt
SULPHIDES
Tonnes
(Millions)
Cu grade
(Tcu%)
Contained
Metal (kt)
Au grade
(g/t)
Contained
Metal (kozs)
Co grade
(ppm)
Contained
Metal (kt)
Proved 219 0.56 1231 0.10 702
Probable 179 0.40 723 0.09 521
Total Reserves
Sulphides
398 0.49 1,954 0.10 1,223
Measured 226.4 0.55 1,252 0.10 715 162 1
Indicated 368.3 0.41 1,501 0.10 1174 131 37
Inferred 570.9 0.37 2,098 0.08 1457 61 48
Total
Resources
Sulphides
1165.6 0.38 4,851 0.09 3,346 73 85
OXIDES
Proved 148.0 0.29 432 0.07 325
Probable 88.0 0.27 234 0.06 170
Total Reserves
Leach
236.0 0.28 665 0.21 495
Measured 255.7 0.32 587
Indicated 216.6 0.27 405
Inferred 71 0.24 116
Total
Resources
Leach
543.30 0.20 1,108
Total Reserves
+ Resources
2,342.90 0.37 8,578.00
Source: https://capstonecopper.com/wp-content/uploads/2024/11/Mantoverde-NI-43-101-Technical-Report-and-Feasibility-
Study_FINAL.pdf
Rule 5.5
ASX Listing Rules Appendix 5B (17/07/20) Page 1
+ See chapter 19 of the ASX Listing Rules for defined terms.
Appendix 5B
Mining exploration entity or oil and gas exploration entity
quarterly cash flow report
Name of entity
Norfolk Metals Limited
ABN Quarter ended (“current quarter”)
38 652 438 385 30 September 2025
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(3 months)
$A’000
1. Cash flows from operating activities
- -
1.1 Receipts from customers
1.2 Payments for
- -
(a) exploration & evaluation #
(b) development - -
(c) production - -
(d) staff costs (185) (185)
(e) administration and corporate costs (188) (188)
1.3 Dividends received (see note 3) - -
1.4 Interest received 19 19
1.5 Interest and other costs of finance paid - -
1.6 Income taxes paid - -
1.7 Government grants and tax incentives - -
1.8 Other (provide details if material) - -
1.9 Net cash from / (used in) operating
activities
(354) (354)
# - These are expenses paid for exploration on the Carmen Copper Project. It is expected that these
expenses will form part of the Earn In exploration expenditure as per the terms of the binding earn
in agreement.
2. Cash flows from investing activities
- -
2.1 Payments to acquire or for:
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) exploration & evaluation (1,087) (1,087)
(e) investments - -
(f) other non-current assets - -
Appendix 5B
Mining exploration entity or oil and gas exploration entity quarterly cash flow report
ASX Listing Rules Appendix 5B (17/07/20) Page 2
+ See chapter 19 of the ASX Listing Rules for defined terms.
Consolidated statement of cash flows Current quarter
$A’000
Year to date
(3 months)
$A’000
2.2 Proceeds from the disposal of:
- -
(a) entities
(b) tenements - -
(c) property, plant and equipment - -
(d) investments - -
(e) other non-current assets - -
2.3 Cash flows from loans to other entities # - -
2.4 Dividends received (see note 3) - -
2.5 Other (provide details if material) - -
2.6 Net cash from / (used in) investing
activities
(1,087) (1,087)
3. Cash flows from financing activities
3,500 3,500
3.1 Proceeds from issues of equity securities
(excluding convertible debt securities)
3.2 Proceeds from issue of convertible debt
securities
- -
3.3 Proceeds from exercise of options - -
3.4 Transaction costs related to issues of equity
securities or convertible debt securities
(233) (233)
3.5 Proceeds from borrowings - -
3.6 Repayment of borrowings - -
3.7 Transaction costs related to loans and
borrowings
- -
3.8 Dividends paid - -
3.9 Other (provide details if material) –
receipt/(payment) of insurance funding
facility
(6) (6)
3.10 Net cash from / (used in) financing
activities
3,261 3,261
4. Net increase / (decrease) in cash and
cash equivalents for the period
4.1 Cash and cash equivalents at beginning of
period
2,104 2,104
4.2 Net cash from / (used in) operating
activities (item 1.9 above)
(354) (354)
4.3 Net cash from / (used in) investing
Share your feedback
Discover